You are leading a digital transformation project for a financial services company. During the execution phase, the compliance team discovers that a new data privacy regulation will take effect in 6 months, requiring significant changes to the data architecture. The development team estimates 4 months of additional work, but the CEO insists on maintaining the original go-live date to capture market opportunities. The change would consume 80% of remaining contingency reserves and requires approval from three different regulatory bodies. What is your best course of action?